Before Installation:
You need to have some equipments and tools such as wrench tool box, gear oil, tow rope, forklift, truck crane.
Single Girder EOT Crane Installation Steps:
1. Fill the gearbox oil
2. end carriage connection
3. bumper installation
4. festoon-rail installation
5. electric box installation
6. electric hoist installation
7. adjust the gap to 3~5mm
8. festoon installation
9. crane hoisting
10. conductor rail installation
11. installation finished.